top of page

Port of Miami Terminal B Renovations

Miami, FL

Client: Port of Miami

SCOPE OF WORK

  • Close design coordination with Customs and Border patrol aspects of incoming baggage which included interrogation offices, holding rooms, detainee areas and the flow of baggage through the disembarkation process.

  • Design of operational arrival / departure customs office at port, including holding and detention components with all security and processing standards for handling security and volatile cases.

  • Necessary security, electrical, mechanical, plumbing, telecommunications and life safety upgrades were completed for Terminal B (approximately 8,000sf), with strict adherence to both the Port of Miami and US Customs and Border Protection standards.


Architect of Record for the renovation of the Port of Miami’s Terminal B facility, Customs and Border Protection.


SQUARE FEET

8,000SF


START / COMPLETED

2009 - 2010